| 1. Construction of Vehicle Service Station complex at Ruderpura:
This world bank aided project was completed in 1993 at an estimated cost of Rs. 35 lacs for Health Department.
2. Construction of Transfer Station complex at Anjana:
This world banks aided project was completed in 1993 at an estimated cost of Rs. 60 lacs for Health Department.
3. Singanpore Weir Project:
The cell carried out major role in co-ordinating between HAIA and SMC for construction of multipurpose project of Singanpore Weir.The construction of weir was completed in 1995 at an estimated cost of Rs. 3500 lacs. The project was financed by (HAIA)Hazira Area Industries Association and after construction was handed over to the Corporation for operation and maintenance according to agreement made. The project has proved to be boon to Surat City. Surat City has flourished tremendously in terms of population and industries during past decade. The corporation provides drinking water to citizens of Surat from the reservoir of weir. HAIA also draws water supply for their industrial requirement needless to say these mega industries have flourished very well and have enhanced prosperity and development in the region. Tidal silting and pollution brought along with tides have been restricted upto the weir in the river.
Ground water salinity ingress in areas u/s. of weir have been reduced considerably due to reservoir of weir. River banks in the reservoir were also subject to tidal erosion prior to construction of weir.
4. Construction of double box RCC storm drain at Rander:
The work was carried out to develop approach road for Singanpore weir at Rander. The work was completed in 1995 at an estimated cost of Rs.40 Lacs.
5. Construction of Control Tower Building at SInganpore Weir:
The work was completed in 1995 at an estimated cost of Rs. 14 Lacs.
6. Erection, testing and commissioning of 2 Nos. 30 mt. high electric Highmast light poles at Singanpore Weir:
The work was completed in 1995 at an estimated cost of Rs.16 Lacs.
7. Fabricating and fixing Chainlink fence at Singanpore Weir:
The work was completed in 1995 at an estimated cost of Rs.10 Lacs.
8. Construction of Transport Godown complex at Puna Kumbharia:
The cell during 2000 carried out supervision work for construction of Transport Godown complex which was built by organiser/builder of Millennium Market on ring road for the old Transport Godown occupants on the plot.
9. Construction of Flood Protection Gates(22 Nos) on outlets of different storm water drains leading to river Tapi:
The department has completed the construction of flood protection gates at 15 locations in the year 1999 at the total cost of Rs.210 lacs. The works were completed in 3 months. Total 22 Nos. of Cast Iron manually operated vertical sliding gates are provided. Normally these gates are kept open, but at the time of heavy floods in the river Tapi, these gates will be closed, to prevent the entry of flood water in to the city.
10. Construction of earthen embankment at Village Tunki, Surat:
As a part of Flood protection scheme on river Tapi Construction of 725 mt. long earthen embankment with rubble pitching was carried out in 2000 at an estimated cost of Rs. 136 lacs.
11. Construction of Sluice regulator at Village Tunki:
As a part of Flood protection scheme on river Tapi Construction of Sluice Regulator on natural creek near Barimata at Tunki was carried out in 2000 at an estimated cost of Rs. 214 lacs.
12. Construction of flood gate structure for Singanpore STP and storm drsin at Bharimata,Surat:
For fasciliating discharge of Singanpore sewage treatment into river and preventing flood water entering into storm box drain of Singanpore area a composite structure was designed and constructed at Bharimata at an estimated cost of Rs. 131 lacs in year 2003.
13. Temporary flood protective work at Rander Panch Pipli temple:
The work was undertaken and completed in 2004 at an estimated cost of Rs.1.00 lacs.
14. Temporary flood protective work at I.P.Mission School, Muglisara:
The work was undertaken and completed in 2004 at an estimated cost of Rs.6.00 lacs.
15. Temporary flood protective work at Bharimata bank:
The work was undertaken and completed in 2004 at an estimated cost of Rs.50.00 lacs.
16. Temporary flood protective work at Singanpore bank:
The work was undertaken and completed in 2004 at an estimated cost of Rs.20.00 lacs.
17. Temporary flood protective work at Bharimata bank:
The work was undertaken and completed in 2005 at an estimated cost of Rs.54.00 lacs.
18. Temporary flood protective work at Singanpore bank:
The work was undertaken and completed in 2005 at an estimated cost of Rs.33.00 lacs.
19. Temporary flood protective work at Ved,Karada and Tunki bank:
The work was undertaken and completed in 2005 at an estimated cost of Rs.14.00 lacs.
20. Bank Protection work at Singanpore bank of river Tapi:
The work was undertaken and completed in 2006 at an estimated cost of Rs.1000.00 lacs.
21. Bank Protection work at Rander bank of river Tapi(Phase-1):
The work was undertaken and completed in 2006 at an estimated cost of Rs.1635.00 lacs.
22. Bank Protection work at Bharimata bank of river Tapi (Phase-1):
The work was undertaken and completed in 2006 at an estimated cost of Rs.1570.00 lacs. |